Rapid work to build our foundation - October 6 & 7
updated October 15
|
Wednesday, October 6, 2004 10:00 am The lot has been cleared and stakes sets to indicate the corners of the foundation. |
|
|
Wednesday, October 6, 2004 3:00 pm By that afternoon, the forms have been set for the foundation. |
|
|
Thursday, October 7, 2004 10:30 am By the next morning, the foundation fill has been put into place. At the far end, this dirt is four feet deep. |
|
|
Monday, October 11, 2004 3:00 pm Plumbing begins to be set in the foundation. This is all PVC pipe which is used for drains and vents. |
|
|
Friday, October 15, 2004 10:00 am Major trenches have been dug. These will become the major beams within the slab when the concrete is poured. Plastic now covers the dirt. |
|